Tuesday, 6 January 2015

Schedule Control #1

Q: What are the performance measurements for the Schedule Control process?

a) SV (PV - EV)  and SPI (PV / EV)
b) SV (EV - AC) and SPI (EV / AC)
c) SV (EV - PV) and SPI (EV / PV)
d) SV (EV - BAC) and SPI (EV / BAC)

A: c)

Schedule Variance (SV) = EV (Earned Value) - PV (Planned Value)
Schedule Performance Index (SPI) = EV / PV

Further definitions:
Earned Value = Estimated value of work actually accomplished on the project
Planned Value = Estimated value of worked planned to be done on the project


Friday, 2 January 2015

Estimates #2

Q: Parametric cost estimating involves

a) Defining the perimeters of the life-cycle
b) Calculating the individual estimates of the work packages
c) Using a statistical algorithm to determine work duration
d) Using the WBS to determine work duration
e) Both a) and d)

A: c)

Tuesday, 14 October 2014

Project Schedule #1

Q: You are a PM for some company, doing some product. You're developing the project schedule and have determined the critical path. Which of the following statements is true?
A: You calculated the early and late start dates, the early and late finish dates, and the float times of activities.

Explanation: The CMP calculates a single early and late start and a single early and late finish date for each activity. Once these dates are known, float time is calculated for each activity to determine the critical path. Other answers typically contain elements of PERT calculations.