Q: You are a PM for some company, doing some product. You're developing the project schedule and have determined the critical path. Which of the following statements is true?
A: You calculated the early and late start dates, the early and late finish dates, and the float times of activities.
Explanation: The CMP calculates a single early and late start and a single early and late finish date for each activity. Once these dates are known, float time is calculated for each activity to determine the critical path. Other answers typically contain elements of PERT calculations.