Q: You are a project manager for an agricultural supply company. You have just completed and obtained sign-off on the project scope statement for your new Natural Bug Busters project. A key stakeholder has informed you that a deliverable is missing from the project scope statement. The deliverable is a critical success factor. Which of the following actions should you take?
a) Modify the scope statement after an approved change request has been received from the stakeholder;
b) Modify the scope statement to reflect the new deliverable;
c) Inform the stakeholder that work not stated in the project scope statement is excluded from the project;
d) Schedule Variance;
e) Inform the stakeholder that this deliverable must be included in phase two of this project since sign-off has already been obtained.
The project scope statement will change throughout the project as a change requests are received and approved. PMs must be certain to discover all deliverables before publishing the project scope statement to prevent situations like the one described in the question.