Sunday, 18 January 2015

Risk Management #4

Q: Response Planning is the responsibility of the functional areas and considers

a) Contingency planning;
b) Unforeseen occurrences;
c) Mitigation;
d) All of the above;
e) Deflection.

A: d)

Thursday, 6 November 2014

Risk Management #3

Q: The risk of accepting a lot of poor quality, in acceptance sampling, is referred to as:

A: Consumer's risk

Wednesday, 15 October 2014

Risk Management #2

Q: Which of the following is most closely associated with pure risk:
Options: a) both 1) profit and loss and 2) market fluctuations; b) personnel turnover; c) profit and loss; d) market fluctuations; e) insurance.
A: e) insurance.


Tuesday, 14 October 2014

Risk Management #1

Q: Several potential risks have been identified on the project. The impact was examined and all the uncertain elements were kept at their baseline values. What type of diagram will be used in the analysis?
A: Tornado diagram

Explanation: The question describes sensitivity analysis, which is a tool and technique of the Quantitative Risk Analysis process. Tornado diagrams are often used to display sensitivity analysis data.