Sunday, 18 January 2015

Planning #1

Q: You are working on a project that is similar in scope to a project performed last year by your company. You might consider which of the following?

a) Using the previous project's alternatives identification as a template;
b) Reusing the previous project's cost-benefit analysis as justification for this project;
c) Reusing the previous project's product description when writing the scope statement;
d) Using the previous project's WBS as a template.

A: d)

WBSs from previous projects can be used as templates on projects that are producing similar products, services, or results. Some companies write WBS templates to be used for projects of similar scope.

Scope Management #4

Q: Your company has asked you to be the project manager for the product introduction of its new DeskTop Rock media system. You recently published the project scope statement. Which of the following is not contained in the project scope statement?

a) Requested changes;
b) Project configuration management requirements;
c) Project specifications;
d) Constraints.

A: a)

Requested changes are an output of the Scope Definition process. They are not part of the project scope statement.


Risk Management #4

Q: Response Planning is the responsibility of the functional areas and considers

a) Contingency planning;
b) Unforeseen occurrences;
c) Mitigation;
d) All of the above;
e) Deflection.

A: d)

Wednesday, 7 January 2015

Scope Management #2

Q: You are a project manager for an agricultural supply company. You have just completed and obtained sign-off on the project scope statement for your new Natural Bug Busters project. A key stakeholder has informed you that a deliverable is missing from the project scope statement. The deliverable is a critical success factor. Which of the following actions should you take?

a) Modify the scope statement after an approved change request has been received from the stakeholder;
b) Modify the scope statement to reflect the new deliverable;
c) Inform the stakeholder that work not stated in the project scope statement is excluded from the project;
d) Schedule Variance;
e) Inform the stakeholder that this deliverable must be included in phase two of this project since sign-off has already been obtained.

The project scope statement will change throughout the project as a change requests are received and approved. PMs must be certain to discover all deliverables before publishing the project scope statement to prevent situations like the one described in the question.

Tuesday, 6 January 2015

Scope management #1

Q: You are working on a project that is similar in scope to a project performed last year by your company. Which of the following might you consider:

a) Reusing the previous project's product description when writing the scope statement
b) Reusing the previous project's cost-benefit analysis as justification for this project
c) Using the previous project's WBS as a template
d) Using the previous project's alternatives identification as a template

A: c) WBSs from previous projects can be used as templates on projects that are producing similar products, services or results. Some companies write WBS templates to be used for projects of similar scope.

Wednesday, 15 October 2014

Project Schedule #2

Q: Your company has appointed you PM for a new product line production. Three new products are involved, two of which will be introduced together, and a third one that will follow within two years. Product number three will be elaborated in more detail closer to its release date, while the first two products will be elaborated in great detail now. The scope management plan has just been completed.  Which of the following is true?
Options:
a) The WBS template from a previous project, a tool and technique of the Create WBS process, was used to create the WBS for this project. The WBS encompasses the major deliverables for the project.
b) The WBS encompasses the full scope of work for the project and the technique in question is called rolling wave planning.
c) Only the deliverables associated with the work of the project should be listed on the WBS. Since product number three isn't being released until a later date it should not  yet be included on the WBS.
d) The WBS should be created next, and it encompasses the full scope of work for the project. Only the work of the project is listed on the WBS.

A: b).
Explanation: There isn't enough information in the question to know whether a) is correct, although it could be. d) is incorrect because the next process after the scope management plan is created is the Scope Definition process. The WBS details the entire scope of the project and includes all deliverables. It is an output of the Create WBS process and the technique of elaborating some deliverables at a later date is called rolling wave planning.

Tuesday, 14 October 2014

Project Schedule #1

Q: You are a PM for some company, doing some product. You're developing the project schedule and have determined the critical path. Which of the following statements is true?
A: You calculated the early and late start dates, the early and late finish dates, and the float times of activities.

Explanation: The CMP calculates a single early and late start and a single early and late finish date for each activity. Once these dates are known, float time is calculated for each activity to determine the critical path. Other answers typically contain elements of PERT calculations.