Wednesday, 7 January 2015

Estimates #4

Q: The ability to achieve cost savings is inversely proportional to _______

a) The estimated costs to complete;
b) None of the other alternatives apply;
c) Empowerment of the PM;
d) The earned value achieved to date;
e) Productivity.

A: d)

In the project initiation phase estimation is rough therefore it can fluctuate -50%  to +100%.


Wednesday, 15 October 2014

Estimates #1

Q: A ________ estimated prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
A: Budget.