Sunday, 18 January 2015

Risk Management #4

Q: Response Planning is the responsibility of the functional areas and considers

a) Contingency planning;
b) Unforeseen occurrences;
c) Mitigation;
d) All of the above;
e) Deflection.

A: d)

Thursday, 8 January 2015

Scope Management #3

Q: You are working with XYZ organisation. Your senior manager imposed a new delivery date which is earlier than the project deliverables date mentioned in the scope statement. To whom are you most accountable?

a) Customer
b) Team members
c) Sponsor
d) Senior Manager

A: a)


Wednesday, 7 January 2015

Scope Management #2

Q: You are a project manager for an agricultural supply company. You have just completed and obtained sign-off on the project scope statement for your new Natural Bug Busters project. A key stakeholder has informed you that a deliverable is missing from the project scope statement. The deliverable is a critical success factor. Which of the following actions should you take?

a) Modify the scope statement after an approved change request has been received from the stakeholder;
b) Modify the scope statement to reflect the new deliverable;
c) Inform the stakeholder that work not stated in the project scope statement is excluded from the project;
d) Schedule Variance;
e) Inform the stakeholder that this deliverable must be included in phase two of this project since sign-off has already been obtained.

The project scope statement will change throughout the project as a change requests are received and approved. PMs must be certain to discover all deliverables before publishing the project scope statement to prevent situations like the one described in the question.

Estimates #4

Q: The ability to achieve cost savings is inversely proportional to _______

a) The estimated costs to complete;
b) None of the other alternatives apply;
c) Empowerment of the PM;
d) The earned value achieved to date;
e) Productivity.

A: d)

In the project initiation phase estimation is rough therefore it can fluctuate -50%  to +100%.


Tuesday, 6 January 2015

Project Charter #1

Q: The project manager is assigned in the
a) Management Plan
b) Charter (contract)
c) SOW
d) Project Plan

A: b)

The Project Manager should be assigned in the early phase of the project otherwise the project may get delayed.


Schedule Control #1

Q: What are the performance measurements for the Schedule Control process?

a) SV (PV - EV)  and SPI (PV / EV)
b) SV (EV - AC) and SPI (EV / AC)
c) SV (EV - PV) and SPI (EV / PV)
d) SV (EV - BAC) and SPI (EV / BAC)

A: c)

Schedule Variance (SV) = EV (Earned Value) - PV (Planned Value)
Schedule Performance Index (SPI) = EV / PV

Further definitions:
Earned Value = Estimated value of work actually accomplished on the project
Planned Value = Estimated value of worked planned to be done on the project


Scope management #1

Q: You are working on a project that is similar in scope to a project performed last year by your company. Which of the following might you consider:

a) Reusing the previous project's product description when writing the scope statement
b) Reusing the previous project's cost-benefit analysis as justification for this project
c) Using the previous project's WBS as a template
d) Using the previous project's alternatives identification as a template

A: c) WBSs from previous projects can be used as templates on projects that are producing similar products, services or results. Some companies write WBS templates to be used for projects of similar scope.