Q: The ability to achieve cost savings is inversely proportional to _______
a) The estimated costs to complete;
b) None of the other alternatives apply;
c) Empowerment of the PM;
d) The earned value achieved to date;
e) Productivity.
A: d)
In the project initiation phase estimation is rough therefore it can fluctuate -50% to +100%.
a) The estimated costs to complete;
b) None of the other alternatives apply;
c) Empowerment of the PM;
d) The earned value achieved to date;
e) Productivity.
A: d)
In the project initiation phase estimation is rough therefore it can fluctuate -50% to +100%.